THE TUNNEL IS NOW FULLY OPERATIONAL AND SHOULD BE USED BY GREEN STAFF, MEMBERS, VISITORS AT ALL TIMES WHEN CROSSING THE BUSY A57

 

  

  Site preparation by the green staff 

 

 

Temp bridge with exposed-telephone cable
(February 13th 2010)

   

Road drains removed and removal of rubble
(February 17th 2010)

  

  Tunnel opening complete
(February 25th 2010)

Rails concreted in for the installation of tunnel section
(March 2nd 2010)

 

Installation of tunnel section
(March 8th 2010) 

 

Drainage channels fitted and base of tunnel fully concreted
(March 11th to 17th)

Installation of tunnel section
(March 8th 2010)

 

 

Side Walls being constructed
(28th March 2010 - 17th April 2010)

 

Side Walls being constructed
(28th March 2010 - 17th April 2010)

 

Side Walls Completed with pathway in place
(17th April 2010)

 

Side Walls being constructed
(28th March 2010 - 17th April 2010)

 

Temp Bridge removed and new road in place
(24th April 2010)

 

North side pathway completed
(12th April 2010)

 

  
Pathway from the 17th to the 18th green 

 

Finished side walls and head wall
Week ending 23rd April 2010